Project Description:
This project includes furnishing and installing a replacement bar screen and hydraulic rake at the City's Kulshan Pump Station to remove debris that blocks the prescreen which is located in the wet well just upstream of the pumps. During large storm events the debris screen can become blocked and backup stormwater upstream of the screen. This is a fairly flat stream system and reducing backups on the pump station screen system will reduce upstream flooding issues.

Funding:
City Storm Water Utility Funded

Project Status:
Bids for this project were opened on September 18, 2018. On October 10, 2018, it was awarded to Harbor Pacific Contractors, Inc., of Woodinville, WA.

Materials are being ordered in January 2019 and will take place during the summer.

This project is expected to to be completed by September 2019.